RESIDENTIAL COMPLEX (LOT 8)
WITH THE UNDERGROUND PARKING LOT AND THE ASSOCIATED INFRASTRUCTURAL OBJECTS
Residential Complex with the underground parking lot and the associated infrastructural objects is projected on the site of the former press shop of the plant ZIL. The conservation of the main facade of the shop facing the Boulevard, is very important for the formation of aesthetically pleasing multi-layered urban environment that has elements of historical identity. From the old shop, there are twin front wall, the coating design with shadow roof light is recreated partially.
In general, the stylobate part forms three above ground floors in the area of a department store, four above ground floors in the area of residential part and two underground floors on the basis of a column grid cell 8,4×8,4 m.
Bearing structures are monolithic reinforced concrete. According to the preliminary design solutions «extension» keeping the facade wall is not involved in the design scheme of the building. Newly constructed concrete structures are not to rely on that wall, but will provide an opportunity to give the facade of the necessary horizontal stiffness.
The historic facade, in turn, is expected to be restored in part of the glazing, to restore the required bearing capacity of the existing number of columns and refresh the color of stucco surfaces.
The entrances to the store from the Boulevard are expected to make through the portals of the historic facade.The department store and part of the apartment complex, as well as necessary to store the technical premises of the complex are located in the 3 — 4 above-ground floors (stylobate).
Four 75-meter tower, «standing» on the podium, include the apartment with the best views. The roof of the stylobate is used as additional space «residential yard.»
The apartments of the 5th floor with access to the roof may have small individual plots in front of the Windows to compensate for the inconveniences associated with living «at ground level». The two underground floors housed the engineering infrastructure elements, download, store, Parking for car owners.
The possibility of compensation for the lack of Parking spaces in the Parking area under the Boulevard (it is expected to make a pedestrian passage in the level — 2 Parking floor). Public Parking, with guest Parking spaces is made off-site and placed under the Boulevard. The pedestrian passage such as an inner «street» faced by the Windows and entrances of the store is cut in the housing complex for better communication between the Boulevard and the residential settlements on the West side in the alignment of the pedestrian street.
The concept provides the use of three main materials for exterior finish: saved walls of the workshops — plaster painted in the «native» gray, walls of a residential complex facing the West side of the building of the first stage — grey «author» brick size 205×100×50 mm, the walls facing the Boulevard — cladding panels with facial finish glass/stemalita.
The specialists of «OPB» performed the following work:
- Development of the design documentation section “Fire Safety Measures” (FSM);
- Development of the special technical requirements (STR) for design and construction in terms of ensuring fire safety;
- Development of design and working documentation for fire protection systems;
- Report on the preliminary planning of military operations for fire departments to extinguish the fire and conduct rescue operations (Fire-fighting plan);